Project 6

– Re-furbish Live Data Centre.
– Clad walls with fire rated plaster boarding, decorate, specialist finishing to concrete ceiling.
– Overhead basket installation, 1,600 cat6, 288 cat6a, 288 OM3, 96 OSI fibre.
– New OM3 fibre backbone to 6 floors.
– Supply and installation of 36 racks, supply and connection of intelligent power poles to racks.
– Extensive cable management system.
– Various server moves.
– Project Management, documentation including cabling topologies.